Lean Manufacturing and Continuous Improvement

OEE and the six big losses

A measure that shows where a line loses its planned time, through the availability, performance and quality factors.

Level:
Practitioner
Who it is for:
Shift supervisor, Maintenance and calibration lead, Plant manager

Definition

OEE is overall equipment effectiveness: it shows how much of a machine's or line's planned production time turns into good product. It is the product of three factors. Availability measures the loss from stoppages, performance the loss from slow running and small stops, and quality the loss from defective output. Planned downtime, such as breaks or planned maintenance, is taken out of the time before the calculation.

OEE (overall equipment effectiveness)

When does it help?

  • People argue about where a line's capacity goes, but nobody can show it in numbers.
  • Maintenance and production disagree about whose area the loss sits in.
  • You want to see whether an improvement really gained time on the line.

When does it not help?

  • Ranking lines with different products, cycles and shift patterns; the same number tells a different story on each line.
  • Comparing operators; OEE measures the loss of the machine and the process, not of a person.

Step-by-step method

  1. Define the line and the ideal cycle

    Write down the line you will measure and the ideal cycle time of one part. The ideal cycle is the shortest time one part takes at the machine's design speed.

  2. Build the stop reasons as a tree

    Write the loss class first and the reasons people use on the floor below it; keep the list short.

  3. Record stops during the shift

    Record each stop with its reason and minutes during the shift; do not write them from memory at the end.

  4. Count the output

    At the end of the shift write the total, scrap and rework counts.

  5. Read the factors one by one

    Look at the three factors before the single number; the lowest factor is your first area of work.

  6. Turn the loss into a task

    Give the cause of the biggest loss to an owner as an improvement task with a due date.

Example scenario

Example scenario

The first month on a press line

On a press line the team records every stop with its reason during the shift for the first month. At month end the quality factor is high and availability is low. When the stop reasons are ranked, changeovers turn out to take longer than breakdowns. The shift supervisor proposes the changeover as the subject of a SMED study for the next month.

A fictional example; the people, company and numbers are not real.

Common mistakes

  • Taking the ideal cycle from the actual speed; performance looks high and the speed loss is hidden.
  • Counting setups and changeovers as planned downtime; the loss with the most room to improve leaves the calculation.
  • Posting only the OEE number on the board; the team cannot see which loss to work on.

Related measure and calculator

Availability, performance, quality and OEE from one shift's stoppages, cycle time and counts; every step shown line by line.

OEE calculator

Templates

  • OEE daily log

    Times and counts per shift; availability, performance, quality and OEE with the same formula as the site's calculator.

    Every template comes in three levels and three formats: Basic is a one-page blank form; Detailed adds guidance and an example row; Complete adds a guide, a filled-in example and a checklist.

    The template files are in Turkish.

Lessons

How does it work in Gemy on the floor?

Company switches onThis module is off in a new company; your administrator switches it on from the Features screen.

Lines, the two-level stop reason tree and the target are company data. A shift record is entered from a phone or by Excel upload. Availability, performance and quality are calculated line by line on the record. The line page shows the trend, the six big losses and a Pareto of losses by reason. An improvement task can be opened from a record below target.

Condition: Switched on by the company. There is no machine connection; records are entered by hand or from Excel.

See it on the product page

Terms

Sources

  1. Overall Equipment Effectiveness, Lean Enterprise Institute (accessed 16 November 2026)
  2. ISO 22400-2:2014 + Amd 1:2017, Automation systems and integration, Key performance indicators (KPIs) for manufacturing operations management, Part 2: Definitions and descriptions, International Organization for Standardization (ISO) (accessed 16 November 2026)
  3. Total Productive Maintenance, Lean Enterprise Institute (accessed 16 November 2026)
  4. Seiichi Nakajima, Introduction to TPM: Total Productive Maintenance. Productivity Press, 1988. ISBN 9780915299232.