OEE and the six big losses

Six big losses and the stop reason tree

Sorting losses into six classes and building a short stop reason tree to use on the floor.

Level:
Practitioner
Who it is for:
Shift supervisor, Maintenance and calibration lead, Lean and OPEX specialist
Duration:
1 min

In this lesson

  • Group the six big losses by factor
  • Build a two-level stop reason tree
  • Rank losses with a Pareto chart

The six big losses are how the total productive maintenance approach classes losses. Each loss falls under one factor. A team that knows this mapping looks for the cause instead of arguing about why the number fell.

Six losses, three factors

  • Breakdowns and setups or changeovers lower availability.
  • Small stops and reduced speed lower performance.
  • Scrap and rework lower quality.

Keep the tree short

On the first level write the loss class: planned downtime, breakdown, setup and small stop. On the second level write the reasons used on the floor, such as waiting for material or a sensor fault. A few reasons under each class are enough.

Do not open an "other" reason, or if you do, check each month how much of the loss lands there. If most losses go to "other", the tree does not speak the language of the floor.

Rank with a Pareto chart

List a month's loss minutes by reason from largest to smallest. If the first few reasons carry most of the loss, start the work there. Repeat the ranking each month; if the top of the list changes, the improvement is working.

Check yourself

There is no score; tap a question to see the answer.

Which factor do small stops belong to?

Performance; the machine is within its run time but makes no parts.

What do you do if a lot of loss lands in "other"?

Rewrite the tree with the reasons used on the floor; it does not speak the floor's language.

Related tool

OEE calculator

Sources

  1. Overall Equipment Effectiveness, Lean Enterprise Institute (accessed 16 November 2026)
  2. Total Productive Maintenance, Lean Enterprise Institute (accessed 16 November 2026)
  3. Seiichi Nakajima, Introduction to TPM: Total Productive Maintenance. Productivity Press, 1988. ISBN 9780915299232.