Calculate the OEE of a shift
Enter the shift length, the stops, the ideal cycle time and the counts. The tool calculates availability, performance, quality and OEE, and shows each intermediate value with its formula.
In short
The OEE calculator turns the figures of a single shift into availability, performance, quality and OEE. The formula is the same as in Gemy's OEE module, and every intermediate value is written out line by line.
- The calculation runs in your browser; nothing is sent
- Every intermediate value is written with its formula under How was this calculated?
- The result is a calculation that rests on the values you enter
- Performance is capped at one; the cap is reported separately
Calculate OEE
Formula: OEE = availability × performance × quality
Result
- OEE
- 74.8%
- Availability
- 88.8%
- Performance
- 86.1%
- Quality
- 97.8%
How was this calculated?
- Planned production time = shift 480 min − planned stops 60 min = 420 min
- Run time = planned production 420 min − breakdowns and setup 47 min = 373 min
- Availability = 373 ÷ 420 = 88.8%
- Ideal time = ideal cycle 1 s × total count 19,271 pcs ÷ 60 = 321.2 min
- Performance = 321.2 ÷ 373 = 86.1%
- Good = total 19,271 − scrap 423 − rework 0 = 18,848 pcs
- Quality = good 18,848 ÷ total 19,271 = 97.8%
- OEE = 88.8% × 86.1% × 97.8% = 74.8%
This is a calculation; it rests on the values you entered.
Small stops do lower OEE. Entering them separately would not change the result: the loss is already measured inside performance, so there is no separate field.
The calculation runs in your browser; the values you enter are not sent anywhere or stored.
Method and formula
OEE shows how much of the planned production time turned into good parts. Stops lower availability, slow running lowers performance and defective parts lower quality. Planned breaks and maintenance are not losses; they are taken out of the planned production time first.
Formula: OEE = availability × performance × quality. Gemy's OEE decision (ADR 0323): Nakajima's six big losses and the ISO 22400-2 definitions.
Related term: read it in the glossary.
Sources
Lean Enterprise Institute, "Overall Equipment Effectiveness".
ISO 22400-2:2014, key performance indicators for manufacturing operations management.
How does it work in Gemy?
Gemy's OEE module uses the same formula. Line figures are entered by hand or from Excel at the end of the shift; no data is read from the machine. The company switches the module on. Related product section.