How availability, performance and quality are calculated and why the same OEE can mean different work.

Level:
Introductory
Who it is for:
Shift supervisor, Maintenance and calibration lead
Duration:
1 min

In this lesson

  • Calculate the three factors from time and counts
  • Tell planned downtime apart from loss
  • Pick the first task from the lowest factor

OEE looks like a single number, but it answers three separate questions. Did the machine run for the time it should have? While it ran, did it run close to its design speed? Were the parts it made good?

Start the clock correctly

Take planned downtime out of the shift time; what remains is planned production time. Breaks, planned maintenance and hours with no production plan are planned downtime. Breakdowns and changeovers are not planned downtime; they are losses.

Calculate the three factors

  • Availability: run time divided by planned production time. Run time is what is left once breakdowns and setups are taken out.
  • Performance: ideal cycle times total count, divided by run time. Small stops and slow running lower this factor.
  • Quality: good count divided by total count. Scrap and rework lower this factor.

OEE is the product of these three factors. Recording small stops separately does not change the result; the loss is already measured inside performance. Recording them separately lets you see the cause of the loss.

Same number, different work

Two lines can show the same OEE. If availability is low on one, the work is in maintenance and changeovers. If quality is low on the other, the work is in process settings and material. So look at the factors first, then go down to the cause.

Check yourself

There is no score; tap a question to see the answer.

Which factor does a changeover lower?

Availability; changeover time is a loss taken out of planned production time.

What happens if you take the ideal cycle from the actual speed?

Performance looks higher than it is and the loss from slow running is hidden.

If two lines have the same OEE, what do you look at?

The three factors one by one; the low factor tells you where the work is.

Related tool

OEE calculator

Sources

  1. Overall Equipment Effectiveness, Lean Enterprise Institute (accessed 16 November 2026)
  2. ISO 22400-2:2014 + Amd 1:2017, Automation systems and integration, Key performance indicators (KPIs) for manufacturing operations management, Part 2: Definitions and descriptions, International Organization for Standardization (ISO) (accessed 16 November 2026)

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice