Field guide
OEE field guide: the first shift record
Preparing the first OEE shift record, the steps during the shift and what you should have at the end of it.
- Level:
- Practitioner
- Who it is for:
- Shift supervisor, Maintenance and calibration lead
Preparation
- Set the line's ideal cycle time together with maintenance.
- Review the stop reason tree with the shift team.
- Write down the shift's start and end time and its planned downtime.
Steps
Record a stop when it happens
Record each stop's reason and length during the shift; if the reason is unknown, use the nearest class and add a note.
Separate the counts
At the end of the shift count the total, scrap and rework separately.
Read the result together
Read the factors with the team; mark the lowest factor and the longest stop reason.
Assign one task
Set an owner and a due date for the longest stop reason.
Output
At the end of the shift you have a list of stops with their reasons and separately counted output. You also have the three factor values and a task for the longest stop reason.
Templates
OEE daily log
Sources
- Overall Equipment Effectiveness, Lean Enterprise Institute (accessed 16 November 2026)
- ISO 22400-2:2014 + Amd 1:2017, Automation systems and integration, Key performance indicators (KPIs) for manufacturing operations management, Part 2: Definitions and descriptions, International Organization for Standardization (ISO) (accessed 16 November 2026)