How to do a risk assessment: the 5x5 matrix and what comes after
In brief
Law No. 6331 and the Risk Assessment Regulation oblige the employer to assess risks. The steps, the right and wrong use of the 5x5 matrix, and where the real work begins after the matrix.
5 November 2026 · 5 min read
Sample company · demo dataRisk page
Türkiye's Occupational Health and Safety Law No. 6331 obliges the employer to carry out or commission a risk assessment. The Occupational Health and Safety Risk Assessment Regulation describes how the work runs: the assessment is done by a team, hazards are identified, risks are analysed, control measures are decided and the work is documented. The regulation also requires the assessment to be renewed at intervals set by hazard class and after certain events. What the legislation asks for is not a table but a living piece of work.
The steps
Team: the employer or deputy, the safety specialist, the workplace physician, the employee representative, support staff and the employees who know the job. An assessment written at a desk does not hold on the floor.
Hazard identification: area by area, machine by machine, job by job. Existing records (near misses, incidents, maintenance, measurements) and conversations with employees provide half the list.
Risk analysis: for each hazard, the likelihood of harm and its severity; the result is a risk level.
Control measures: measures that bring the risk to an acceptable level; owner and due date.
Documentation and renewal: the work is written and signed by the team; it is renewed within the period in the regulation or after an event, a change or a new hazard.
What the 5x5 matrix is and is not
The 5x5 matrix scores likelihood and severity from one to five and reads the product. The result is a number between one and twenty-five, which the company divides into low, medium and high bands. The matrix's value lies not in the number but in the comparison: it says which of two risks to handle first. There are things the matrix does not do: a single number does not prove acceptability, scores must not be lowered as if a measure were already in place, and not every hazard fits the same scale.
Define the likelihood and severity scales in writing: everyone must understand “likelihood 3” the same way.
Score first the raw risk as if no control were in place, then the residual risk with existing controls; keep the two scores apart and give the residual score again once a planned control is in place.
Set the acceptable level in advance; do not move the threshold after seeing the score.
Do not trade severity against likelihood: a fatal but rare risk is not less important than a frequent but minor one.
After the matrix: the hierarchy of controls
The real work starts after the score. The US National Institute for Occupational Safety and Health (NIOSH) ranks controls in five levels: eliminate the hazard, substitute something less hazardous, engineering controls, administrative controls and personal protective equipment. The upper levels are more effective because they rely on the condition, not on human behaviour. The most frequent mistake in risk assessments is a list that ends with training and PPE only; that leaves the hazard in place and moves the responsibility to the employee.
HSE's guidance on managing risk recommends the same order and describes the purpose of an assessment as protecting people rather than producing paper. A good assessment can be short; what matters is that every hazard ends in a measure and every measure in an owner.
How the work stays alive
Every near miss and incident is linked to the relevant hazard row; the score is asked again.
A change of machine, material or process triggers the assessment; a link is made to management of change.
Measures are tracked as actions; an unclosed measure invalidates a score lowered on paper.
The annual review is done with the team; unchanged rows are read too, because the condition may have changed.
A fictional example
On a paint line the hazard “solvent vapour” had been scored likelihood three, severity four, and written into the medium band with twelve points. The measure column held only “use of masks”. When the team renewed the assessment it first measured the existing ventilation; the extraction point was on the wrong side of the paint booth. The team moved one level up the hierarchy of controls: the extraction point was relocated, a lock was added to the booth door, and the mask remained as the last level. The residual score was given again with the existing controls, and two dates were written on the row: the date of the measurement and the next review. What changed was not the score but the condition the score rested on.
Sample company · demo dataRisk registers
How it is done in Gemy
Risk registers are scored with the company's own scales; likelihood and impact scales, colour thresholds and the acceptable risk level come from settings. Separate registers can be kept for quality, OHS and information security.
Each risk row holds the source, likelihood, impact, current control and the actions opened; measures are tracked as actions and closed with evidence.
Rows are edited in the spreadsheet view; if the floor plan module is on, a risk pin appears on the plan.
If the management of change module is on, a risk assessment item lands on a change request's impact list; the change cannot close until the item is complete.
The product does not replace the team work and the signatures the regulation requires; it records the assessment and tracks its measures.
In short
A risk assessment is the team work the law requires and the regulation lays out step by step. The 5x5 matrix is a tool for ranking risks, not proof of acceptability. The real work begins after the matrix: the highest feasible level of the hierarchy of controls is chosen, every measure is tied to an owner and a due date, and every event and change reopens the assessment. This article is general information, not legal advice.
You may copy and share this article with attribution (Gemy, https://www.gemydigital.com/en/blog/risk-degerlendirmesi-nasil-yapilir-5x5-matris-ve-sonrasi).
Every solved problem is a piece of knowledge; in most companies it leaves with the person who solved it. The four places where knowledge is lost, the view of ISO 30401 and ISO 9001, and five habits that make knowledge independent of people.
A supplier audit is a process, not a visit: which supplier, which question, which finding, which evidence. The audit principles of ISO 19011, the structure of the question list, finding classes and how the reply returns to the same record.
Document control ensures the right version of the right document is with the right person. What ISO 9001 asks for, document types and numbering, the approval chain, distribution and reading, withdrawing the old version and the five most common gaps.