Measuring the changeover, putting each step into internal or external and taking external steps out of the stoppage.
- Level:
- Introductory
- Who it is for:
- Shift supervisor, Lean and OPEX specialist
- Duration:
- 1 min
In this lesson
- Measure changeover time from the right points
- Put each step into internal or external
- Write a preparation list for the external steps
The first stage of SMED asks for order, not investment: finishing the external steps before the stop. Once you separate the work done while the machine is stopped that could be done without waiting, the stoppage shortens by itself.
Measure the changeover end to end
Start the clock at the last piece of the completed run and stop it at the first good piece of the new run. Trial parts and adjustment are part of the changeover. Video the changeover; the video shows the steps beyond argument.
Watch the video with the team and write each step on a line. Put the step's name, its time and who did it on the line.
Ask every step the same question
"Can this step be done while the machine runs?" If yes, the step is external. Fetching the die from the store, finding a tool and preparing a document are external examples. Removing the old die and clamping the new one are internal.
- Every tool someone looks for marks an external step.
- Waiting is a step too; write it down with its time.
- A step that must be done with the machine stopped for safety stays internal.
Finish external steps before the stop
Write a preparation list for the external steps and check it before the changeover. Gathering everything needed on a cart is one way to make this preparation.
Check yourself
There is no score; tap a question to see the answer.
Between which two points is changeover time measured?
Between the last piece of the completed run and the first good piece of the new run.
How do you know a step is external?
If it can be done while the machine runs, it is external.
Related tool
Sources
- Single Minute Exchange of Die, Lean Enterprise Institute (accessed 16 November 2026)
- Shigeo Shingo, A Revolution in Manufacturing: The SMED System. Productivity Press, 1985. ISBN 9780915299034.
- Changeover, Lean Enterprise Institute (accessed 16 November 2026)