Calculate the saving on a changeover

Enter the changeover steps with their durations and choose whether each step is internal or external today. Then pick a target for each step: keep it, move it outside, shorten it or eliminate it.

In short

The SMED savings calculator compares the time the machine stands still during a changeover today and in the target. The formula is the same as the SMED calculation in Gemy's time study.

  • The calculation runs in your browser; nothing is sent
  • Every intermediate value is written with its formula under How was this calculated?
  • The result is a calculation that rests on the values you enter
  • Only internal steps count towards the stoppage; external steps are shown separately

Calculate the SMED saving

Formula: Saving = today's internal steps − target internal steps

Sample values
Step 1

Leave it empty to keep today's duration.

Step 2

Leave it empty to keep today's duration.

Step 3

Leave it empty to keep today's duration.

Step 4
Step 5

Leave it empty to keep today's duration.

Result

Saving
26 min
Stoppage today
40 min
Target stoppage
14 min

How was this calculated?

  1. Stoppage today = sum of internal steps = 12 + 8 + 15 + 5 = 40 min
  2. External steps today = 10 min (done while the machine runs, not part of the stoppage)
  3. Target stoppage = sum of the steps that stay internal = 8 + 6 + 0 = 14 min
  4. External steps in the target = 22 min
  5. Saving = 40 − 14 = 26 min
  6. Saving percentage = 26 ÷ 40 × 100 = 65%

This is a calculation; it rests on the values you entered.

Parallel steps are not in this tool: every step is counted one after another. In Gemy's time study the longest of the parallel steps at the same position is counted.

The calculation runs in your browser; the values you enter are not sent anywhere or stored.

Method and formula

Film the changeover and write each step down separately. A step done while the machine is stopped is internal; a step that can be done while it runs is external. The saving comes from moving internal steps outside, shortening them or eliminating them.

Formula: Saving = sum of today's internal steps − sum of target internal steps. Gemy's time study decision (ADR 0196) and Shigeo Shingo's split of internal and external steps.

Related term: read it in the glossary.

Sources

Lean Enterprise Institute, "Single Minute Exchange of Die".

Toyota, Toyota Production System.

How does it work in Gemy?

Gemy's time study times SMED steps with a stopwatch and splits them into internal and external. It keeps the before / after comparison with the same formula; the company switches the module on. Related product section.

Other calculators

Every calculator and template, from OEE to the risk score, on one page.

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice