8D problem solving and CAPA
The eight steps of 8D
The order of the eight steps, the output of each and which step must not be skipped.
- Level:
- Introductory
- Who it is for:
- Quality engineer
- Duration:
- 1 min
In this lesson
- List the eight steps in order
- Tell containment from permanent action
- Name the output of each step
8D takes its name from its eight-step structure, and each step is called a discipline. A discipline here means a step and the output it leaves behind. Each step feeds the next, so the order matters.
The first three steps: team, description, protection
In the first step the team is formed. In the second the problem is written in measurable terms: which part, which line, which date range and how many. In the third a containment action protects the customer; sorting or an extra check are examples.
The middle steps: cause and action
In the fourth step the root cause is sought and verified. In the fifth and sixth the permanent action is chosen and applied, and the containment is lifted.
The last two steps: preventing recurrence and recognition
In the seventh step the change is carried into instructions, the control plan and similar processes. In the eighth the team's work is recognised and the record is closed.
- Containment protects the customer; it does not remove the cause.
- The permanent action targets the verified root cause.
- If the seventh step is skipped, the same problem appears on another line.
Check yourself
There is no score; tap a question to see the answer.
What is the difference between containment and permanent action?
Containment protects the customer; the permanent action removes the verified root cause.
What happens if the seventh step is skipped?
The change is not carried into the standard or similar processes, so the same problem reappears elsewhere.