Field guide
SMED field guide: the first changeover analysis
Preparing the first SMED analysis, recording the changeover and what you should have at the end of it.
- Level:
- Practitioner
- Who it is for:
- Shift supervisor, Lean and OPEX specialist
Preparation
- Choose the changeover to analyse and its date with the team that does it.
- Get the team's agreement to filming and choose where to film from.
- Prepare an empty table or a time study form for the step list.
Steps
Film the changeover
Film without a break from the last piece of the completed run to the first good piece of the new run. Ask the team to work as usual.
List the steps
Watch the video with the team; write each step, its time and who did it.
Mark internal and external
Decide together for each step whether it can be done while the machine runs.
Pick the first tasks
Set a preparation list and an owner for the external steps to move out of the stoppage.
Output
At the end of the analysis you have a step list with times, and each step is marked internal or external. You also have a preparation list for the external steps and its owner.