TPM autonomous maintenance steps: cleaning, inspection, lubrication

In brief

Autonomous maintenance means the person who knows the machine best, the operator, takes over its daily care. The content of the first three steps, the abnormality tag, the CIL standard and the division of work between operator and maintenance.

7 November 2026 · 5 min read

Sample company · demo dataAction detail: owner, due date, who assigned it and the “Started / Done” buttons
Action detail

Total productive maintenance (TPM) is an approach in which operators, maintenance and management reduce machine losses together; the Japan Institute of Plant Maintenance (JIPM) is its origin and its awarding body. The Lean Enterprise Institute lexicon describes TPM as the set of methods that ensures every machine can always perform its required task in the production process. Autonomous maintenance is the first pillar of TPM and rests on a simple premise: the person who uses the machine every day notices its sound, smell and vibration before anyone else.

Why the operator?

The maintenance team sees the machine when it breaks down; the operator sees it every shift. A small leak, a loosening bolt or a dirty sensor is visible for weeks before it becomes a breakdown. Autonomous maintenance uses those weeks: the operator cleans, inspects while cleaning, and tags the abnormality while inspecting. The maintenance team, in turn, spends its time on planned work and improvement instead of chasing breakdowns. The operator does not become a maintenance technician; they become the daily owner of their machine.

The first three steps

  • Initial cleaning: the machine is cleaned thoroughly, as a team. The aim is not to polish but to see by touching; every abnormality found during cleaning gets a tag. The number of tags from the first cleaning surprises most companies.
  • Eliminating sources of contamination and hard-to-reach places: the leaks, dust and chip sources that make cleaning necessary every day are closed off; a window or a transparent cover is made for points that cannot be checked without opening a guard. Cleaning time drops.
  • A provisional cleaning, inspection and lubrication standard (CIL): what is cleaned, inspected and lubricated, how often, in how many minutes and with what. The standard is written with the operator, at the machine, with photos.

The later steps (general inspection training, autonomous inspection, organisation and self-management) build on these three; a company that moves to the fourth before the first three have settled usually ends up back at the first.

The abnormality tag

A tag is the operator's way of reporting to maintenance a condition they saw and cannot fix themselves: a leak, looseness, wear, a missing cover, a dead gauge. Two colours are common: a tag the operator can resolve and a tag for maintenance. Every tag has a number, a photo, an owner and a closing date. The value of a tag lies not in its count but in its closing time: a tag left open for weeks tells the operator that reporting is pointless, and the next tag is never written.

Writing the CIL standard

  • Points on the machine are numbered; for each point a cleaning, inspection or lubrication task is written.
  • Each task has a frequency (start of shift, daily, weekly), a duration and the material to be used.
  • For inspection points the normal condition is defined: a pressure range, an oil level line, a sound. Without knowing normal, abnormal cannot be noticed.
  • The total time must fit inside the shift; if it does not, the machine or the time is changed, not the standard.
  • The standard carries photos and a version; it is updated when an improvement is made.

Division of work between operator and maintenance

Autonomous maintenance does not mean dumping the maintenance team's work on the operator. The operator takes on daily cleaning, inspection, simple lubrication and tightening; the maintenance team takes on planned maintenance, breakdown repair, inspections that need measurement and the operator's training. The boundary must be written down, and work beyond the operator's capacity goes to maintenance through a tag. The manager's job is not to set the two against each other but to follow the tag closing time with both.

A fictional example

On a packaging machine the initial cleaning day team was the operator, a maintenance technician and the team leader. After four hours seventeen tags had been written: three leaks, four loose connections, two dead gauges, one missing cover and corners that could not be cleaned. The operator closed five of the tags the same day; the maintenance team closed twelve within two weeks. In the third week a removable tray was made under the conveyor for the corners that could not be cleaned, and daily cleaning time halved. In the fourth week the provisional CIL standard was written at the machine, with photos. The machine's only unplanned stop in the next three months came from a leak the operator had noticed and tagged first; but this time maintenance was done before the leak became a breakdown.

Sample company · demo dataTime study (SMED): current and target downtime, time gain and external time
Time study

How it is done in Gemy

  • Autonomous maintenance checklists (CIL) are filled in from a phone; a tag is opened for any abnormality seen.
  • A tag closes on the action backbone: owner, due date and evidence photo in one place; a tag past its due date shows as overdue.
  • If the floor plan module is on, the tag pin appears on the plan.
  • Focused improvement runs as a Kobetsu Kaizen project: the loss, the team, steps, target and minutes.

TPM is a module the company switches on if it wishes; it does not connect to machines and reads no sensor or meter data. The content of the standard is the company's knowledge.

In short

Autonomous maintenance means the person who uses the machine every day takes over its daily care. The first three steps come in order: deep initial cleaning with tagging, eliminating contamination sources and hard-to-reach places, and a photographed CIL standard. The value of a tag lies in its closing time, not its count. The boundary between operator and maintenance is written down; the operator becomes the daily owner of the machine and the maintenance team moves from chasing breakdowns to planned work.

Sources

You may copy and share this article with attribution (Gemy, https://www.gemydigital.com/en/blog/tpm-otonom-bakim-adimlari-temizlik-kontrol-yaglama).

Related posts

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice