From claimed to verified savings
Measuring and verifying a claimed saving
Writing the baseline and method in advance, adjusting for changed conditions, giving verification to someone else and checking that the gain lasts.
- Level:
- Practitioner
- Who it is for:
- Strategy and planning lead, Lean and OPEX specialist
- Duration:
- 1 min
In this lesson
- Write the baseline and the measurement method in advance
- Compare after adjusting for differences in conditions
- Report the estimate and the verified amount separately
An improvement's gain is born as an estimate in the application. The estimate helps decision making, but it is not a realised gain. Verification replaces the estimate with a measurement.
Write the plan first
EVO asks for a measurement and verification plan for each project; the plan defines how the saving is reported. Write the plan before the change and set the following:
- Which measure is followed: scrap, downtime, energy use.
- The baseline period: which months before the change.
- The measurement period: which months after the change.
- The source of the unit cost that turns the measure into money.
Adjust for differences in conditions
The baseline and the measurement period do not run under the same conditions. If output went up, total scrap may also go up; so compare scrap per unit. Make the adjustment with a rule written in the plan, not one chosen after measuring.
How detailed the measurement is depends on the size of the expected saving and the risk that it will not be achieved. The U.S. Department of Energy guidance asks for this proportion: the larger the saving and the higher the risk, the stricter the measurement.
Give verification to someone else
The person who wrote the claim does not approve their own gain. Finance or an authorised person reads the measurement and verifies the amount, sends it back for correction or rejects it. The estimate and the verified amount stay side by side; the gap between them is a lesson for the next estimate.
Measure again to see if it lasts
A verified gain can erode over time. Repeat the same measurement on set days and compare the share kept with the gain at verification. If no measurement was made, write the result as missing data, not as a loss.
Check yourself
There is no score; tap a question to see the answer.
Why can a saving not be measured directly?
A saving describes consumption that did not happen; so the baseline is compared with the period after the change.
How do you compare scrap if output went up?
By scrap per unit rather than the total; I write the adjustment rule in the plan in advance.
What is written if no retention measurement was made?
Missing data, not a loss; the result is read once the measurement is made.
Sources
- IPMVP (International Performance Measurement and Verification Protocol), Efficiency Valuation Organization (EVO) (accessed 16 November 2026)
- Measurement and Verification for Federal Energy Savings Performance Contracts, U.S. Department of Energy, Federal Energy Management Program (FEMP) (accessed 16 November 2026)