Management of change (MOC)

Assessing and approving the impact of a process, equipment, material or software change before it is made, and closing it only after the linked work.

Level:
Practitioner
Who it is for:
Quality engineer, Safety specialist, Maintenance and calibration lead, Plant manager

Definition

Management of change is assessing and approving the impact of a change to a process, equipment, material, software or organisation before it is made. OSHA's rule for processes with highly hazardous chemicals asks for five points to be addressed before a change. These are the technical basis, the impact on safety and health, changes to operating procedures, the time needed and the authorisation required. The same rule asks for affected workers to be informed and trained before start-up. A replacement in kind, one that satisfies the design specification, does not count as a change under this rule.

Management of change (MOC)

When does it help?

  • A part, a setting limit or the control software of a machine is going to change.
  • A change of raw material, chemical or supplier could affect the product or the workers.
  • A temporary fix is going in and could become permanent if its end is not tracked.

When does it not help?

  • Replacing a part with one of the same kind and specification; that is maintenance work.
  • A daily setting within the limits the instruction allows; that is part of the job.

Step-by-step method

  1. Write the change as a request

    State in the request what will change, why, and which area it will affect.

  2. Set its type and duration

    Write whether the change is permanent or temporary; a temporary one has an end date.

  3. List the impact

    Write down the linked work one by one: risk assessment, FMEA, instructions, training, calibration and maintenance.

  4. Tie approval to risk

    The higher the risk of the change, the more units take part in approval; the approver is a competent person who knows the job.

  5. Finish the linked work

    Update the instruction, inform and train the affected workers; then start up.

  6. Check before start-up

    See on site that the change was made as designed and that all the linked work is done.

  7. Review effectiveness

    After a period of running, check whether the change gave the expected result and whether it created a new hazard.

Example scenario

Example scenario

A different type of hydraulic pump on a press

In a plastic injection workshop the maintenance team opens a request to replace a press's hydraulic pump with a different type. FMEA, risk assessment, the maintenance instruction and operator training go on the impact list; the risk row shows higher possible pressure. Hose and cylinder ratings are checked; the relief valve is set not to exceed the lowest rating, sealed and written into the instruction. The press runs only after the operators have read the new instruction and the start-up check is done.

A fictional example; the people, company and numbers are not real.

Common mistakes

  • Opening a temporary change without an end date; the temporary fix stays in place for years.
  • Thinking about impact only in terms of safety; quality, training and maintenance work is forgotten.
  • Looking only at the spot where the change is made; a change on one line can affect a distant section too.
  • Starting up before the instruction is updated; the operator runs the new machine with the old method.

Lessons

How does it work in Gemy on the floor?

Company switches onThis module is off in a new company; your administrator switches it on from the Features screen.

Change types and the impact list template of each type are company data. When the impact assessment starts, items are created from the type's current version; FMEA, risk, document revision, training and device checks are among them. An item marked as not applicable needs a reason and is written to the request's history. Approval goes through the company's approval flow; the approval type is chosen in the settings by risk level. The company can also set a risk level to need no approval. The request does not close until the required items are done and the actions opened from it are verified. If the company writes screening questions for a type, a request with a “yes” answer is flagged as a candidate substantial change for machinery safety. It cannot go to approval until an expert the company authorises enters the result; the legal assessment is your company's.

Condition: Switched on by the company.

See it on the product page

Terms

Sources

  1. 1910.119 Process safety management of highly hazardous chemicals, (l) Management of change, Occupational Safety and Health Administration (OSHA) (accessed 16 November 2026)
  2. Plant modification / Change procedures, Health and Safety Executive (HSE) (accessed 16 November 2026)
  3. Makine Emniyeti Yönetmeliği (Resmî Gazete 16.10.2026, sayı 33402), T.C. Resmî Gazete (accessed 16 November 2026)

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice