Catching failures early with FMEA

From FMEA to prevention and the control plan

Separating prevention from detection, choosing a mistake-proofing device and linking the row to the control plan.

Level:
Practitioner
Who it is for:
Quality engineer, Plant manager
Duration:
1 min

In this lesson

  • Tell prevention and detection controls apart
  • Choose an action for a priority row
  • Link the row to an item in the control plan

An FMEA table on its own changes nothing. Change comes from the action taken on priority rows and from checking that action on the floor.

Separate prevention from detection

A prevention control stops the failure from happening; a detection control catches it before it reaches the customer.

Look for prevention first

On a priority row the first question is how the failure could never happen. A part that cannot be fitted the wrong way or a machine that will not run with a missing step is mistake-proofing. If prevention is not possible, choose a control that catches the failure the moment it happens.

  • Give every action an owner and a due date.
  • Once the action is done, score the row again and keep the first score.
  • If a row is still a priority after rescoring, look for a new action.

Link it to the control plan

The control plan says what is checked on the floor, how, how often and within which limits. The control of every priority row should match an item in the plan. Also write what to do on an out-of-limit result, that is, the reaction plan.

Check yourself

There is no score; tap a question to see the answer.

What is the difference between a prevention control and a detection control?

Prevention stops the failure from happening; detection catches it before it reaches the customer.

What is the first question on a priority row?

What can be done so that the failure never happens.

What does the reaction plan in a control plan say?

What to do when an out-of-limit result appears.

Sources

  1. IEC 60812:2018 Failure modes and effects analysis (FMEA and FMECA), International Electrotechnical Commission (IEC) (accessed 16 November 2026)
  2. Poka Yoke, Lean Enterprise Institute (accessed 16 November 2026)