Calculate the balance loss of a line

Enter the work time and waste time of each station, and the takt time if you have it. The tool calculates the bottleneck, balance efficiency, balance loss and the fewest stations needed.

In short

The Yamazumi balance loss calculator shows how evenly the station loads are spread against the bottleneck. Balance efficiency uses the formula in Gemy's time study; balance loss is its complement.

  • The calculation runs in your browser; nothing is sent
  • Every intermediate value is written with its formula under How was this calculated?
  • The result is a calculation that rests on the values you enter
  • Waste time does not count towards the fewest stations needed

Calculate the line balance

Formula: Balance efficiency = Σ loads ÷ (bottleneck × stations); balance loss = 100 − balance efficiency

Sample values

You can leave it empty; then no takt comparison is made.

Station 1

Value-adding and necessary work.

Walking, waiting, searching and the like; 0 if none.

Station 2

Value-adding and necessary work.

Walking, waiting, searching and the like; 0 if none.

Station 3

Value-adding and necessary work.

Walking, waiting, searching and the like; 0 if none.

Station 4

Value-adding and necessary work.

Walking, waiting, searching and the like; 0 if none.

Result

Balance loss
19.5%
Balance efficiency
80.5%
Bottleneck
64 s
Fewest stations needed
4

How was this calculated?

  1. Station 1 load = 48 + 4 = 52 s
  2. Station 2 load = 55 + 9 = 64 s (above takt)
  3. Station 3 load = 38 + 2 = 40 s
  4. Station 4 load = 50 + 0 = 50 s
  5. Bottleneck = longest load = 64 s
  6. Sum of loads = 206 s
  7. Balance efficiency = 206 ÷ (64 × 4) × 100 = 80.5%
  8. Balance loss = 100 − 80.5 = 19.5%
  9. Fewest stations needed = ⌈ sum of work times 191 ÷ takt 60 ⌉ = 4 (waste not counted)

This is a calculation; it rests on the values you entered.

Each row is a one-person station. In Gemy's time study a column is split by station and person, and steps are classed as value-adding, necessary or waste.

The calculation runs in your browser; the values you enter are not sent anywhere or stored.

Method and formula

A Yamazumi chart stacks the work of each station. The tallest column is the bottleneck and sets the pace of the line. The gap in the shorter columns is the balance loss; you close it by moving work between stations or removing waste at the bottleneck. The tool adds waste to the station load; the fewest stations needed does not count waste.

Formula: Balance efficiency = Σ station loads ÷ (bottleneck × number of stations); balance loss = 100 − balance efficiency. Gemy's time study decision (ADR 0196); the balance loss is derived from the product's balance efficiency.

Related term: read it in the glossary.

Sources

Lean Enterprise Institute, "Operator Balance Chart".

Lean Enterprise Institute, "Takt Time".

How does it work in Gemy?

Gemy's time study stacks the steps of a Yamazumi study into station and person columns and draws the takt line. Balance efficiency uses the same formula. The company switches the module on. Related product section.

Other calculators

Every calculator and template, from OEE to the risk score, on one page.

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice