Tools
Calculate the balance loss of a line
Enter the work time and waste time of each station, and the takt time if you have it. The tool calculates the bottleneck, balance efficiency, balance loss and the fewest stations needed.
In short
The Yamazumi balance loss calculator shows how evenly the station loads are spread against the bottleneck. Balance efficiency uses the formula in Gemy's time study; balance loss is its complement.
- The calculation runs in your browser; nothing is sent
- Every intermediate value is written with its formula under How was this calculated?
- The result is a calculation that rests on the values you enter
- Waste time does not count towards the fewest stations needed
Calculate the line balance
Formula: Balance efficiency = Σ loads ÷ (bottleneck × stations); balance loss = 100 − balance efficiency
Result
- Balance loss
- 19.5%
- Balance efficiency
- 80.5%
- Bottleneck
- 64 s
- Fewest stations needed
- 4
How was this calculated?
- Station 1 load = 48 + 4 = 52 s
- Station 2 load = 55 + 9 = 64 s (above takt)
- Station 3 load = 38 + 2 = 40 s
- Station 4 load = 50 + 0 = 50 s
- Bottleneck = longest load = 64 s
- Sum of loads = 206 s
- Balance efficiency = 206 ÷ (64 × 4) × 100 = 80.5%
- Balance loss = 100 − 80.5 = 19.5%
- Fewest stations needed = ⌈ sum of work times 191 ÷ takt 60 ⌉ = 4 (waste not counted)
This is a calculation; it rests on the values you entered.
Each row is a one-person station. In Gemy's time study a column is split by station and person, and steps are classed as value-adding, necessary or waste.
The calculation runs in your browser; the values you enter are not sent anywhere or stored.
Method and formula
A Yamazumi chart stacks the work of each station. The tallest column is the bottleneck and sets the pace of the line. The gap in the shorter columns is the balance loss; you close it by moving work between stations or removing waste at the bottleneck. The tool adds waste to the station load; the fewest stations needed does not count waste.
Formula: Balance efficiency = Σ station loads ÷ (bottleneck × number of stations); balance loss = 100 − balance efficiency. Gemy's time study decision (ADR 0196); the balance loss is derived from the product's balance efficiency.
Related term: read it in the glossary.
Sources
Lean Enterprise Institute, "Operator Balance Chart".
Lean Enterprise Institute, "Takt Time".
How does it work in Gemy?
Gemy's time study stacks the steps of a Yamazumi study into station and person columns and draws the takt line. Balance efficiency uses the same formula. The company switches the module on. Related product section.