Find the takt time of a line

Enter the daily net working time and the number of pieces the customer takes each day. The tool calculates the takt time per piece and the output needed per hour.

In short

The takt time calculator divides the net working time by customer demand to find the pace per piece. The formula is the same as the takt calculation in Gemy's time study.

  • The calculation runs in your browser; nothing is sent
  • Every intermediate value is written with its formula under How was this calculated?
  • The result is a calculation that rests on the values you enter
  • Takt is rounded to one decimal; it is not calculated if time or demand is zero

Calculate takt time

Formula: Takt time = net working time ÷ customer demand

Sample values

All shifts, with breaks and planned stops taken out.

The average number of pieces the customer takes in one day.

Result

Takt time
90 s
In minutes
1.5 min
Output needed per hour
40 pcs

How was this calculated?

  1. Net working time = 900 min × 60 = 54,000 s
  2. Takt time = 54,000 s ÷ 600 pcs = 90 s (rounded to one decimal)
  3. In minutes = 90 s ÷ 60 = 1.5 min
  4. Output needed per hour = 3,600 s ÷ 90 s = 40 pcs

This is a calculation; it rests on the values you entered.

Takt is the pace the customer asks for, not the machine speed. If the cycle time is longer than takt, the line falls behind demand.

The calculation runs in your browser; the values you enter are not sent anywhere or stored.

Method and formula

Takt tells you the pace at which the customer takes the product. Only time set aside for production goes into the net time; breaks and planned stops are taken out first. A station whose cycle time is longer than takt slows the line down.

Formula: Takt time = net working time ÷ customer demand. Gemy's time study decision (ADR 0196) and the Lean Enterprise Institute definition of takt.

Related term: read it in the glossary.

Sources

Lean Enterprise Institute, "Takt Time".

Toyota, Toyota Production System.

How does it work in Gemy?

Gemy's time study calculates takt time with the same formula and draws it as the takt line on the Yamazumi chart. The company switches the module on. Related product section.

Other calculators

Every calculator and template, from OEE to the risk score, on one page.

Cookies

Essential cookies are needed for the site to work. Analytics cookies load only if you allow them; declining is as easy as accepting. You can change your choice at any time via the footer link.

Cookie policyPrivacy notice